●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates t

(75)
A、 analyze
B、 track
C、 level
D、 extend

发布时间:2025-09-03 16:38:49
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:正确答案:B