A business analyst (BA) assigned to a project has been asked to implement regulatory requirements based on priority.What type of traceability relationship can the BA use to find an the solution components that need to be implemented?


A、 Satisfy
B、 Dependency
C、 Validate
D、 Derive

发布时间:2025-07-31 14:35:07
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:A