 A company uses activity-based costing to calculate the unit cost of its products. The figures for Period 3 are as follows: production set-up costs are $84,000. Total production is 40,000 units of each of products A and B, and each run is 2,000 units of A or 5,000 units of B. What is the set-up cost per unit of B?

 A company uses activity-based costing to calculate the unit cost of its products. The figures for Period 3 are as follows: production set-up costs are $84,000. Total production is 40,000 units of each of products A and B, and each run is 2,000 units of A or 5,000 units of
B、 What is the set-up cost per unit of B?

发布时间:2025-07-21 00:43:46
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:$0.60