The following statements refer to situations occurring in Process Q of an organisation which operates a series of consecutive processes:(i) Direct labour is working at below the agreed productivity level.(ii) A machine breakdown has occurred.(iii) Direct labour is waiting for work to be completed in a previous process.Which of these situations could give rise to idle time?
A、(i) and (ii) only;
B、(i) and (iii) only;
C、(ii) and (iii) only;
D、(i), (ii) and (iii)