You are working on your research and development project when your customer asks you to include a particular component in the project. You know this represents new work, and you do not have excess funds available . What should you do?

.Delete another lower priority task to make more time and funds available.
B、Use funds from the management reserve to cover the cost.
C、Follow the contract change control process.
D、Ask for more funds from the project sponsor.

发布时间:2025-02-27 19:21:12
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:C
Therequestfromthecustomerisachangeandshouldbehandledasachange.ChoiceAandBborderonunethical.