Which statement about the Tendering Procedure is not true?


A、Tendering is the process of selecting the most suitable contractor for constructing the project.;
B、In most cases, the successful tenderer will be the one submitting the “lowest evaluated substantially responsive bid”.;
C、The contractor who receives the Letter of Acceptance will be the successful tenderer.;
D、Prequalification is not recommended for major projects.

发布时间:2025-07-20 02:25:44
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:Prequalification is not recommended for major projects.