200A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.What should the project manager have done to avoid this issue?
A、Prioritized blockers on the critical path
B、Distributed the daily standup meeting agenda beforehand
C、Followed the quality control measurements
D、Developed the team members' competences: