NO.17 One of the key stakeholders came to you asking you to add more metrics because she thinks that it would give the portfolio management a better view of the actual progress. For her the more metrics you have the better. What should your opinion be regarding this?
A、 You should agree as having more metrics is better and because you do not want to say no to a key stakeholder
B、 You should agree, as having more metrics is better
C、 You should disagree and communicate a clear message to the stakeholder that it does not matter how many metrics you have as long as you can fully report the progress
D、 You should disagree and escalate this to the governance board