15If a project manager communicates a verbal message to a subordinate, and the subordinate
、15 If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:
A、 the message was understoodB the message was not understood
C、 the subordinate discarded the information
D、 the information was not appropriate
E、 None of the above