.An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed What action should the project manager take?


A、 Escalate the issue from the IT team to management and get the validation prioritized
B、 Work with the IT team to prioritize the validation and release of the new features
C、 Deliver the features when the IT team is able to validate them
D、 Request the IT team to immediately release the product and then validate the features

发布时间:2025-10-29 09:14:16
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:B