: An agile team of a software development project has been rewarded with a higher hourly billing rate because they have completed the work earlier than the contractual deadline. What is the contract type followed in the Agile team’s project?


A、 Time
B、 Fixed
C、 Cost
D、 Graduated

发布时间:2026-01-31 10:12:29
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:D