.A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?


A、 Ask the product owner, who is the key stakeholder, to choose among the different ideas.
B、 Propose ideas to the group, ask everyone to vote, and then choose the most popular idea
C、 Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.
D、 Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

发布时间:2025-10-15 04:01:00
推荐参考答案 ( 由 快搜搜题库 官方老师解答 )
联系客服
答案:C